Progress to Date

 
  • May 2016

    Negotiated option to purchase land in an off-market transaction

  • Summer 2016

    Master plan design

  • October 2016

    Initial presentation to Town of Gardiner Planning Board

  • March 2017

    Planning Board EAF application and development plan submitted

  • June 2017

    Ulster County Planning Board review; Environmental Conservation Commission review

  • July 2017

    Fire department review; Board of Health review and well testing; Department of Transportation review

  • August 2017

    Three months of public hearings

  • September 2017

    Closed on purchase of land; Department of Environmental Conservation review

  • May 2018

    Environmental Review completed - SEQR Negative Declaration granted by Planning Board

  • Winter 2018

    Final site plan approval (anticipated)

  • Spring 2019

    12-14 months construction begins

  • Spring/Summer 2020

    Heartwood opens for business